Current Construction Projects

2019 MFT & Capital Westside Resurface Program 

Arrow Road Construction was awarded this project. 

These improvements are funded with both Motor Fuel Tax and Village Capital funds. Work will consist of 2-inch surface removal and replacement, select base repair, select sidewalk and curb & gutter replacement, pedestrian upgrades, ADA complaint upgrades, minor structure maintenance, pavement markings and restoration. Areas include select streets in the Kimball Farms subdivision, South Washington St., Illinois St., Highland Ave., and Hillside St. 

This project is complete.

Westside Resurface Map 1

Westside Resurface Map 2

2019 MFT Sidewalk Removal and Replacement Program

Strada Construction Co. was awarded this project. Work began August 5th. 

The Village spends approximate $125k per year in Motor Fuel Tax funds maintaining sidewalks by removing failed sections of sidewalk throughout the Village. Areas of select replacement  for 2019 will be along Sparrow Rd., Hampton Dr., Kingston Cir., Roanoke Ave., and Blue Ridge Dr.  

This project is complete. 

Sidewalk R & R Map  

2019 CDBG & Capital Eastside Resurface Program

Triggi Construction was awarded this project. Work began July 5th. 

These improvements are funded with Village Capital funds. Approximately 50% of this project will be reimbursed to the Village with grant funding awarded by the Kane County Community Development fund program. Work will consist of 2-inch surface removal and replacement, select base repair, carriage walk removal, sidewalk and curb & gutter placement, pedestrian upgrades, ADA complaint upgrades, minor structure maintenance, pavement markings and restoration. These improvements will be completed on Navajo Dr. between Helm Rd. and Papoose Rd.

This project is complete.

Eastside Resurface Map

Hopi Lane Drainage Improvements

Bolder Construction was awarded this project. Work began August 2nd 

These improvements are located in the neighborhood near the northeast of IL-25 and Helm Road. Work will consist of replacing and up-sizing the existing storm sewer, adding additional storm sewers, water and sanitary improvements, new roadway including curb & gutter and sidewalk. Work is scheduled to begin mid summer.

Construction is on-going. water main improvements are complete. Storm sewer improvements are complete with the exception of the connection to the existing state storm sewer on IL-25. This connection is currently being re-designed due to a conflict with an AT&T duct.  Curb and gutter is complete and roadways has been paved to binder level. Final surface is expected to be completed the first week of November. 

Hopi Lane Storm Sewer Map

Keith Andres Memorial Park Stream Restoration Project 

In 2018 the Village was awarded $648,507 in EPA Section 319 funds through the Illinois Environmental Protection Agency. These funds will cover approximately 60% of the construction costs.  

The Village has contracted with CBBEL to complete the engineering services for the grant application and the final design for construction improvements that will stabilize approximately 4,000 feet of eroded stream bank along both sides of the Lake Marian Creek with Keith Andres Memorial Park. Other improvements include the installation of 26 pool/riffle sequence grade control structures, removal of a section of failing concrete lined channel, regrading, stone toe protection,, raising and lowering the channel bottom grade in various locations, filling in the downstream to recreate a single channel with proper morphology, and restore 2 acres of adjoining riparian woodland by removing non-native vegetation. Permit approvals are pending and construction is anticipated to begin late summer or early fall.

Keith Andres Project Map

Typical Proposed Cross Section

Longmeadow Parkway Project

This project is under the jurisdiction of the Kane County Division of Transportation. To obtain updates, status and view exhibits and maps of the overall project limits visit the Kane County Division of Transportation website.

Illinois Route 31 & Huntley Road/Main Street Improvement Project

Visit the dedicated website for updates and status of this construction project.

Huntley Road Improvement Project

This is joint improvement project with the Village of West Dundee with the Village of West Dundee being the lead agency. Visit the Village of West Dundee's website for updates and status of this construction project.